Restauration Continued
Finally we can continue the work
{vsig}Synagoge/2014-Herbst|sort=1 {/vsig}
{vsig_c}0|2014-11-21.jpg||21-11-2104, Start: The damaged floor will be removed {/vsig_c}
{vsig_c}0|2014-11-24.jpg||24-11-2104, Digging deeper{/vsig_c}
{vsig_c}0|2014-11-28.jpg||28-11-2104, Firm ground has been reached. The structural engineer has given his oK.{/vsig_c}
{vsig_c}0|2014-12-05.jpg||05-12-2104, The basis for the new floor has been laid.{/vsig_c}
{vsig_c}0|2014-12-05_2.jpg||05-12-2104, Preparations for the electric installations.{/vsig_c}
{vsig_c}0|2014-12-08.jpg||08-12-2104, Putting in insolation.{/vsig_c}
{vsig_c}0|2014-12-14.jpg||14-12-2104, Preparation for the final stage: The reinforcement for the concrete and the electrical fittings are in place.{/vsig_c}
{vsig_c}0|2014-12-15.jpg||15-12-2104, The new floor is there but very wet.{/vsig_c}
{vsig_c}0|2014-12-19.jpg||19-12-2104, The concrete is covered for slow drying.{/vsig_c}
{vsig_c}0|2015-01-23.jpg||23-01-2015, The protective wall-covering has been removed – the synagogue starts to look nice again.{/vsig_c}